Another aspect to this project was the manufacture of a stainless steel mixer tank, this would be the holding vessel to which the chemicals are mixed. After welding the tank we conducted a leak detection test before the tank left our fabrication workshop, a test certificate was then issued to the client. As the tank could not be transported with motor and shaft in tact, this was all installed on site by our own engineers. The mixer was installed carefully onto load cells and fixed firmly to the floor in its correct position. After the mixer was installed our site teams then installed the services which included compressed air, water lines, acid lines, and a 200mm UPVC extraction duct. To the success of this project we are now negotiating a further two mixing stations.